Without quantities
Contents |
[edit] Introduction
The term ‘without quantities’ refers to a construction contract or tender documents that do not include specific measured quantities of the items of work identified by the drawings and specifications. It can be used on projects where it is not possible to prepare a bill of quantities (BOQ) at the time of tendering. This might be because the design is progressed enough for tendering purposes but not firm enough to provide accurate quantities.
Smaller projects, or alteration work may also be tendered without quantities, for example where a schedule of works is prepared allowing the pricing of items, such as builders' work and fixing schedules. For more information see: Schedule of works.
An intermediate position between the two approaches is ‘approximate quantities’. For more information see: Approximate quantities.
[edit] Contract features
Tendering on the basis of “without quantities” can allow selection of the contractor and so expedite the project program. Generally, the design will be relatively complete, but may be insufficient time or information to determine the quantities. Drawings, specifications and schedules will generally form the key contract documents if projects are procured in this way.
Procuring ‘without quantities’ will result in a lump sum contract. There will be no re-measurement required and it can simplify the valuation process. This might initially give cost certainty for the client but there can be disadvantages later if variations are required, and there is disagreement about the rates to be charged for changes. A pricing document might be prepared during the tender stage, but it might not be detailed enough to capture all rates that could apply to changes. The drawings, specification and schedules should therefore capture as much detail as possible to minimise variations.
[edit] JCT contracts
The JCT Standard Building Contract is an example of a contract that can be used without quantitates. JCT give the following guidance for contracts ‘without quantities’:
- The project is generally not complex enough to require bills of quantities.
- The employer must provide drawings together with a description of works, and either a specification or work schedules at tender stage.
- The price and payment structure is based on a lump sum with monthly interim payments.
- Pre-construction services agreements can be used with this contract.
- This contract can be used with a framework agreement.
- This contract can be used for both private and public sector projects.
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities.
- Bill of quantities.
- Contract documents.
- Form of contract.
- Lump Sum.
- Procurement route.
- Schedule of works.
- Tender documents.
- Tender pricing document.
- Types of bill of quantities.
- Unpriced bill.
[edit] External references:
Featured articles and news
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building 2024 judges choice winner
Once Upon a Pass by Liam Man.
CIOB Art of Building 2024 public choice winner
Fresco School by Roman Robroek.
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
How orchards can influence planning and development.